NTIS 바로가기전기학회논문지 = The Transactions of the Korean Institute of Electrical Engineers, v.66 no.11, 2017년, pp.1561 - 1567
임현옥 (Smart Grid Research Center, Dept. of Electrical Engineering, Chonbuk National University) , 최우영 (Smart Grid Research Center, Dept. of Electrical Engineering, Chonbuk National University) , 권한나 (Smart Grid Research Center, Dept. of Electrical Engineering, Chonbuk National University) , 국경수 (Dept. of Electrical Engineering, Chonbuk National University)
This paper calculates the effective capacity of EES providing the primary frequency control service based on its contribution to the frequency response of the power system. The amount of governor response from conventional generators which can be replaced by the primary frequency control from EES ke...
* AI 자동 식별 결과로 적합하지 않은 문장이 있을 수 있으니, 이용에 유의하시기 바랍니다.
핵심어 | 질문 | 논문에서 추출한 답변 |
---|---|---|
전기저장장치의 장점은? | 최근 신재생발전원이 급격히 확충되어 전력계통의 유연성 제고에 대한 필요성이 높아지고, 휴대용 전기제품 시장의 급격한 성장과 기술의 발달로 배터리의 경제성이 개선됨에 따라 전력계통의 운영에도 전기저장장치를 적극적으로 적용하고자 하는 노력들이 활발히 이루어지고 있다[1][2]. 특히 전기저장장치는 기존의 화력 발전기에 비해 응답속도가 매우 빠르고, 충·방전을 통한 제어범위가 넓어 전력계통의 주파수운영예비력을 제공하는 자원으로 활용되는 것이 매우 효과적인 것으로 알려지고 있다. | |
주파수 추종서비스의 역할은? | 2Hz 변동 시 응답가능용량을 기준으로 산정하며, 상정고장 후 10초 내에 발전력이 응동하여 30초 이상 출력을 유지할 수 있어야 한다. 이러한 주파수추종서비스는 대용량 발전기 탈락과 같은 계통 고장 발생 시 자동발전제어의 관여 없이 가장 빠르게 응동하여 전력계통의 주파수가 하락하는 것을 막고 일정 수준 이상으로 유지되도록 한다. 따라서 전력계통에서 확보해야 하는 주파수추종 서비스의 요구량은 전력계통 운영에서 최대단위 발전기 탈락 시를 기준으로 유지하고자 하는 주파수 수준에 따라 결정하는 것으로 알려져 있다[5]. | |
전기저장장치의 제어전략은 어떻게 구분하여 적용되고 있는가? | 상용운전 중인 전기저장장치의 제어전략은 전력계통의 주파수 변동에 따라 정상상태와 과도상태로 구분하여 적용되고 있다[8]. 과도상태 제어전략의 경우, 외란 발생 시 전기저장장치의 용량을 최대한 활용하도록 주파수 제어를 수행하고 있으며,[9] 정상상태의 경우 주파수 부동대 이내에서는 전기저장장치의 충전상태를 유지하기 위한 제어를 수행하며, 주파수 부동대 이외의 범위에서는 기존 화력 발전기와 유사한 수준으로 주파수제어를 수행한다[10]. |
"K-ESS 2020", Ministry of Trade, Industry and Energy, May, 2011
"KEMRI Power Economics Review", KEPCO Economy & Management Research Institute (KEMRI), No. 41, pp. 1-7, Oct 26, 2015
Power System Operations Guide, KPX, Dec, 2016
"KEPCO plan for Frequency Regulation using ESS", Journal of the Electric World, Vol. 461, pp. 12-17, May, 2015
"Evaluation of Supply Reserve and Operating Reserve Requirements Considering Enlargement of Power System Scale", KPX, Dec, 2011
Ga Ram Yu, "Integrated Control Strategy of Multiple BESS for providing Primary Frequency Control", The Transactions of the KIEE, Vol. 65, No. 7, pp. 1169-1175, Jul 2016
Woo Yeong Choi, "Operating Method of BESS for Providing AGC Frequency Control Service Considering Its Availability Maximization", The Transactions of the KIEE, Vol. 65, No. 7, pp. 1161-1168, Jul 2016
"Development of Control Algorithm of ESS for Frequency Regulation in Power System", KEPRI-Chonbuk National University, 2015.11.30.
Jun Bum Han, "A Study on the Criteria for Setting the Dynamic Control Mode of Battery Energy Storage System in Power Systems", The Transactions of KIEE, Vol. 62, No. 4, pp. 444-450, Mar. 2013
Jun Yeong Yun, "SOC-based Control Strategy of Battery Energy Storage System for Power System Frequency Regulation" The Transactions of KIEE Vol. 63, No. 5, pp. 622-628, May, 2014
Frequency response initiative report, North American Electric Reliability Corporation (NERC), Oct 30, 2012
Performance Based Regulation: Year One Analysis, Regulation Performance Senior Task Force, PJM Interconnection, Oct 12, 2013
Anforderungen an die Speicherkapazitat bei Batterien fur die Primarregelleistung, Transmission System Operators: 50 Hertz, Amprion, Tennet, Transnet BW, Sep 29, 2015
*원문 PDF 파일 및 링크정보가 존재하지 않을 경우 KISTI DDS 시스템에서 제공하는 원문복사서비스를 사용할 수 있습니다.
※ AI-Helper는 부적절한 답변을 할 수 있습니다.