NTIS 바로가기한국건축시공학회지 = Journal of the Korea Institute of Building Construction, v.20 no.6, 2020년, pp.527 - 535
이치주 (Construction Economy & Industry Research Division, Korea Research Institute for Human Settlements) , 권태욱 (Construction Administration Team, POSCO Engineering & Construction) , 고훈석 (Shinpyeongtaek LNG Power Plant Construction Site, POSCO Engineering & Construction)
This study analyzed main causes of claims in EPC/Turnkey projects. For this purpose, this study referred to the FIDIC silver book, which lists the international standard contract conditions for EPC/Turnkey projects. The most frequent cause of claim was delay. A process was then proposed to determine...
* AI 자동 식별 결과로 적합하지 않은 문장이 있을 수 있으니, 이용에 유의하시기 바랍니다.
Daube D, Vollrath S, Alfen HW. A comparison of project finance and the forfeiting model as financing forms for PPP projects in Germany. International Journal of Project Management. 2008 May;26(4):376-87. https://doi.org/10.1016/j.ijproman.2007.07.001
Merrow EW. Industrial megaprojects: concepts, strategies, and practices for success. Hoboken:John Wiley &Sons; 2011. 384p.
Jun SH. Problem analysis and improvement strategy for overseas plant construction by EPC lump-sum turnkey system [master thesis]. [Seoul (Korea)]: Chung-Ang University; 2009. 95 p.
Kwon TW. The framework development of EPC project claims management system[master thesis]. [Pohang (Korea)]. Pohang University of Science and Technology. 2015. 98 p.
Kululanga GK, Kuotcha W, McCaffer R, Edum-Fotwe F. Construction contractors' claim process framework. Journal of Construction Engineering and Management. 2001 Aug;127(4):309-14.https://doi.org/10.1061/(ASCE)0733-9364 (2001)127:4(309)
Hartman FT, Snelgrove P, Ashrafi R. Appropriate risk allocation in lump-sum contracts-who should take the risk. Cost Engineering. 1998 Jul;40(7):21-6.
Construction Industry Institute. Equitable risk allocation: a legal perspective. Texas: Construction Industry Institute, Austin. 2007. 62 P.
Kim SH. The research on standard contract conditions of oversea construction project(FIDIC) [master thesis]. [Seoul (Korea)]: Seoul National University. 2014. 394 p.
Ashley DB, Dunlop JR, Parker MM. Impact of risk allocation and equity in construction contracts: an overview of indemnification, consequential damages, differing conditions &delay clauses. Texas: Construction Industry Institute, Austin. 1988. 432 p.
Ibbs CW. Determining the impact of various construction contract types and clauses on project performance. Texas: Construction Industry Institute, Austin. 1986. 227 p.
Scott S, Harris RA. United kingdom construction claims: views of professionals. Journal of Construction Engineering and Management. 2004 Oct;130(5):734-41. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:5(734)
Abdul-Malak MAU, El-Saadi MMH, Abou-Zeid MG. Process model for administrating construction claims. Journal of Management in Engineering. 2002 Apr;18(2):84-94. https://doi.org/10.1061/(ASCE)0742-597X(2002)18:2(84)
Hegab MY, Nassar KM. Decision support system for commencement delay claims. Practice Periodical on Structural Design and Construction. 2005 Aug;10(3):177-80. https://doi.org/10.1061/(ASCE)1084-0680(2005)10:3(177)
Ko HS. Risk analysis of contractual provisions for EPC/Turnkey projects: Contractor''s liability position [master thesis], [Pohang (Korea)]: Pohang University of Science and Technology. 2014. 97p.
The international Federation of Consulting Engineers. Conditions of contract for EPC/Trunkey projects. Geneva: The international Federation of Consulting Engineers (FIDIC); 1999. 122 p.
The society of construction law. The society of construction law delay and disruption protocol. 2nd ed. Leicestershire: The society of construction law; 2002. 84 p.
※ AI-Helper는 부적절한 답변을 할 수 있습니다.