NTIS 바로가기KSCE Journal of Civil and Environmental Engineering Research = 대한토목학회논문집, v.43 no.1, 2023년, pp.109 - 117
박종호 (성균관대학교 리질리언트에코스마트시티) , 조민건 (성균관대학교 글로벌스마트시티융합공학과) , 엄세호 (성균관대학교 글로벌스마트시티융합공학과) , 박선규 (성균관대학교 건설환경공학부)
Schedule delays present a major risk factor, as they can adversely affect construction projects, such as through increasing construction costs, claims from a client, and/or a decrease in construction quality due to trims to stages to catch up on lost time. Risk management has been conducted accordin...
Al-Bahar, J. F. (1989). Risk management in construction projects: a?systemic analytical approach for contractors, Ph.D. Dissertation,?University of California Berkeley, Berkeley, California, USA.
Choi, J. W. (2015). An analysis on regional differences of major?delay factors in overseas architectural projects, Master. Dissertation,?Hanyang University, Seoul, Korea (in Korean).
Devlin, J., Chang, M. W., Lee, K. and Toutanova, K. (2019).?"BERT: Pre-training of deep bidirectional transformers for?language understanding." arXiv:1810.04805v2, pp. 1-16.
Kang, H. B. and Yi, J. S. (2018). "An analysis of public text data in?construction disaster cases using Word2Vec-based data visualization." Autumn Annual Conference of AIK, 2018, Architectural?Institute of Korea, Vol. 38, No. 2, pp. 567-570 (in Korean).
Kang, L. S., Kim, C. H. and Kwak, J. M. (2002). "Analysis for the?importance of risk factors through the project life cycle." Journal?of the Architectural Institute of Korea Structure & Construction,?Vol. 17, No. 8, pp. 103-110 (in Korean).
Kim, J. S. (2022). Analysis of project delay using big data, Master.?Dissertation, Hanyang University, Seoul, Korea (in Korean).
Kim, J. S. and Kim, B. S. (2019). "Characteristics analysis of seasonal?construction site fall accident using text mining." Korean Journal?of Construction Engineering and Management, Vol. 20, No. 3,?pp. 113-121 (in Korean).
Lee, H. C., Lee, J. H. and Go, S. S. (2009). "A study on the priority?analysis of work delay factors in steal-frame work using FMEA."?Construction Engineering and Management, Vol. 10, No. 1, pp.?91-101 (in Korean).
Lee, H. K. (2018). A risk assessment model for delay management?protocol in the contract conditions of international construction?projects, Ph.D. Dissertation, Ajou University, Suwon, Korea (in?Korean).
Lee, J. H. and Yi, J. S. (2017). "Predicting project's uncertainty risk?in the bidding process by integrating unstructured text data and?structured numerical data using text mining." Applied Sciences,?Vol. 7, No. 11, pp. 1-15.
Marzouk, M. and Enaba, M. (2019). "Text analytics to analyze and?monitor construction project contract and correspondence." Automation in Construction, Vol. 98, pp. 265-274.
Park, G. S. (2012). A study on the estimation of an appropriate?construction duration of apartment, Master. Dissertation, Seoul?National University of Science and Technology, Seoul, Korea (in?Korean).
Park, J. H., Choi, H. S., Cho, Y., Bang, K. S., Yun, S. H. and Paek, J.?H. (2010). "A study on the development of probabilistic duration?estimation module using monte carlo simulation." Journal of the?Architectural Institute of Korea Structure & Construction, Vol.?26, No. 5, pp. 101-108 (in Korean).
Park, K. C. and Kim, H. K. (2021). "Analysis of seasonal importance?of construction hazards using text mining." KSCE Journal of?Civil and Environmental Engineering Research, KSCE, Vol. 41,?No. 3, pp. 305-316 (in Korean).
Project Management Institute (PMI) (2021). A guide to the project?management body of knowledge (PMBOK Guide), Project?Management Institute, Newton Square, PA.
Son, B. Y. and Lee, E. B. (2019). "Using text mining to estimate?schedule delay risk of 13 oshore oil and gas EPC case studies?during the bidding process." Energies, Vol. 12, No. 10, pp. 1-25.
Vaswani, A., Shazeer, N., Parmar, N., Uszk oreit, J., Jones, L.,?Gomez, A. N., Kaiser, L. and Polosukhin, I. (2017). "Attention is?all you need." arXiv:1706.03762v5, pp. 1-15.
Wang, G., Liu, M., Cao, D. and Tan, D. (2020). "Identifying high-frequency-low-severity construction safety risks: An empirical?study based on official supervision reports in Shanghai." Engineering,?Construction and Architectural Management, Vol. 29, No. 2, pp.?940-960.
Yang, H. S. (2020). Comparison of recognition on the risks affecting?schedule delays and cost overruns in overseas civil construction?projects, Master. Dissertation, Hanyang University, Seoul, Korea?(in Korean).
Yoon, J. K. (2017). A study to derive delay factors based on?international standard contract at building construction in the?south-east Asia, Master. Dissertation, University of Seoul, Seoul,?Korea (in Korean).
Yoon, J. S. (2020). Development of method for quantifying and?applying non-working day to planning and scheduling to calculate?normal project duration, Ph.D. Dissertation, Ajou University,?Suwon, Korea (in Korean).
Yoon, Y. S., Suh, S. W., Park, M. S. and Jang, M. H. (2008).?"Construction process based schedule risk management system."?Construction Engineering and Management, Vol. 9, No. 4, pp.?101-110 (in Korean).
Yu, Y. J., Son, K. Y., Kim, T. H. and Kim, J. M. (2017). "A basic?study on cost prediction model based on repair and replacement?causes by using probabilistic forecasting concept - focused on?educational facilities." Architecture & City in JEJU, Architectural?Institute of Korea, Vol. 37, No. 1, pp. 887-890 (in Korean).
*원문 PDF 파일 및 링크정보가 존재하지 않을 경우 KISTI DDS 시스템에서 제공하는 원문복사서비스를 사용할 수 있습니다.
오픈액세스 학술지에 출판된 논문
※ AI-Helper는 부적절한 답변을 할 수 있습니다.